Utilizing a hybrid fuzzy DEMATEL-ANP-Delphi approach for identifying and prioritizing construction cost overruns in project management

Document Type : Research Paper

Authors

1 Department of Civil Engineering, Yazd Branch, Islamic Azad University, Yazd, Iran

2 Department of Management, Yazd Branch, Islamic Azad University, Yazd, Iran

Abstract

Construction projects are frequently associated with a high incidence of cost overruns. To address this issue, the present study adopts a descriptive and survey-based approach to identify and rank the factors that contribute to construction costs. The study's statistical population comprises ten expert specialists, and the fuzzy Decision-Making Trial and Evaluation Laboratory (DEMATEL) with Analytical Network Process (ANP) (DANP) technique is utilized to evaluate the research factors. Additionally, the fuzzy DANP and Delphi methods are employed to rank the essential dimensions and criteria of the research. The study's findings reveal that environmental factors are the primary cause of construction cost overruns, followed by managerial factors and legal and administrative factors, respectively. Dynamic conditions often result in unpredictable challenges for environmental factors, making them a critical driver of construction cost overruns. Therefore, environmental factors play a significant role in contributing to construction cost overruns.

Keywords

[1] F. Afzal, S. Yunfei, M. Nazir, and S.M. Bhatti, A review of artificial intelligence-based risk assessment methods for capturing complexity-risk interdependencies: Cost overrun in construction projects, Int. J. Manag. Projects Bus. 14 (2019), no. 2, 300–328.
[2] B. Akomah, J. Mensah, Z. Mustapha, and S. Kottey, Cost impacts of variations on building construction projects, MedCrave Online J. Civil Engin. 4 (2018), no. 5, 386–392.
[3] G.B.S. Alekhya, K. Shashikanth, and M.A. Prasad, Risk assessment of cost overrun using fuzzy logic model, Mater. Today: Proc. 62 (2022), 1803–1810.
[4] T. Amri and M. Marey-Perez, Towards a sustainable construction industry: Delays and cost overrun causes in construction projects of Oman, J. Project Manag. 5 (2020), no. 2, 87–102.
[5] W.-Y. Chiu, G.-H. Tzeng, and H.-L. Li, A new hybrid MCDM model combining DANP with VIKOR to improve e-store business, Knowledge-based Syst. 37 (2013), 48–61.
[6] I. Gurkhani, M. Mohammadi, and A. Sabet, Identifying the effective factors on the occurrence of delays and cost increases in case study of Mehr Housing projects, 1st Nat. Conf. Manag. Ethics Bus., Shiraz, Iran, 2019.
[7] M. Hejazi and R. Norouzpour, The role of project integration management in reducing construction project costs, 7th Nat. Conf. Account. Manag. Appl., Tehran, Iran, 2015.
[8] M.S. Islam, M. Nepal, and M. Skitmore, Modified fuzzy group decision-making approach to cost overrun risk assessment of power plant projects, J. Constr. Eng. Manag.-ASCE 145 (2019), no. 2.
[9] M. Juszczyk, The challenges of nonparametric cost estimation of construction works with the use of artificial intelligence tools, Proc. Eng. 196 (2017), 415–442.
[10] S. Kanchana and A. Sukumaran, A critical study on cost escalation in construction industry, Int. J. Eng. Technol. Manag. Res. 5 (2018), no. 2, 194–197.
[11] M. Khalilzadeh and R. Mohammadi, Factors affecting increasing the cost of construction projects in construction projects (Qazvin city), 12th Int. Conf. Project Manag., Tehran, Iran, 2017.
[12] A. Lesniak and K. Zima, Cost calculation of construction projects including sustainability factors using the case-based reasoning (CBR) method, J. Sustain. 10 (2018), no. 5, 1–14.
[13] A.Q. Memon, A.H. Memon, M. Soomro, and I. Rahman, Common factors affecting time and cost performance of construction projects in Pakistan, Pakistan J. Sci. 71 (2019), no. 4, 64–68.
[14] T. Nyoni, Towards factors affecting delays in construction projects: A case of Zimbabwe, Dynamic Res. J. J. Econ. Finance 2 (2017), no. 1, 12–28.
[15] J.I. Obianyo, O.E. Okey, and G.U. Alaneme, Assessment of cost overrun factors in construction projects in Nigeria using fuzzy logic, Innov. Infrast. Solut. 7 (2022), no. 5, 1–20.
[16] A. Pirasteh, Studying factors affecting the increase in delays and costs of construction projects, 2nd Conf. Civil Engin. Architect. Urban Plann. Islamic World, Tabriz, Iran, 2018.
[17] M.A. Ronald and S. Agung, Analysis of project cost management and the effect on cost overrun in construction projects, Int. J. Innov. Res. Sci. Eng. Technol. 7 (2018), no. 7, 8049–8054.
[18] A. Sen, A.K. Dwivedi, and M.K. Trivedi, Evaluation of rework factors affecting cost and schedule performance in construction projects, Int. Res. J. Eng. Technol. 5 (2018), no. 8, 489–497.
[19] S.K. Seyedebrahimi, A.R. Mirjalili, and A. Sadeghian, Identification and prioritization of factors influencing the increase in construction costs of building investments using factor analysis, Arch. Civil Engin. 67 (2021), no. 3, 705–722.
[20] S. Sharma and P.K. Goyal, Fuzzy assessment of the risk factors causing cost overrun in construction industry, Evol. Intell. 15 (2022), 2269–2281.
[21] N. Thakur, Cost overrun and time delay risk assessment in local road bridge construction using fuzzy inference system, Doctoral dissertation, Pulchowk Campus, 2021.
[22] I. Zafar, I.Y. Wuni, G.Q. Shen, S. Ahmed, and T. Yousaf, A fuzzy synthetic evaluation analysis of time overrun risk factors in highway projects of terrorism-affected countries: the case of Pakistan, Int. J. Constr. Manag. 22 (2022), no. 4, 732–750.
Volume 16, Issue 4
April 2025
Pages 83-92
  • Receive Date: 30 July 2023
  • Accept Date: 23 September 2023